Civic Center Paving Project


DATE:       AUGUST 23, 2013

PHASE 1 A Commences 4/15/2013:  COMPLETED 05/10/2013

PHASE 1 B Commences 05/13/2013:  COMPLETED 06/08/2013

PHASE 2 Commences 06/08/2013:  COMPLETED 07/19/2013

PHASE 3 Commences 07/22/2013:  COMPLETED 08/24/2013

Residents and employees can conitnue to expect minor delays, detours and temporary parking lot closures when using the West Bloomfield Township Civic Center this summer. 

On Monday, August 26, Phase 4 will begin. In this phase we will start by closing the inbound Civic Center drive for construction.  The Civic Center outbound drive will be converted into two-way traffic. When the construction of the inbound drive is completed, we will switch traffic to the newly completed drive and close the outbound drive for reconstruction.  We will also be improving the geometrics of the intersection with a right turn deceleration lane and the traffic signal will be upgraded. 

..............................................................................................................................

Again, the project consists of the reconstruction of Civic Center Boulevard and rehabilitation of all the Civic Center Complex parking lots and sidewalks.  Improvements to the complex drainage system are also included.  New curbing will be installed and sidewalks will be repaired. Access to each building and pathway in the complex shall remain open during the project.  We anticipate project completion to be by the end of September.

 

The project is divided into five phases and will require visitors and employees to park in specific areas to facilitate the construction. We appreciate your patience as you navigate through each phase of the project this summer.

 

Again, West Bloomfield Township greatly appreciates your patience as you navigate through the complex this summer.  This investment in the township will provide safer roads; smoother parking lots, increased water quality in our wetlands, and improved access to all complex facilities for many years to come.

 

 

Civic Center Parking Lot Reconstruction

 

Phase 1A  --COMPLETED

Phase 1 B  -- COMPLETED
Phase 2 -- COMPLETED

Phase 3 -- COMPLETED

Phase 4 -- Civic Center Drive Reconstruction

August 24, 2013 thru September 30, 2013

On Monday, August 26, Phase 4 will begin. In this phase we will start by closing the inbound Civic Center drive for construction.  The Civic Center outbound drive will be converted into two-way traffic. When the construction of the inbound drive is completed, we will switch traffic to the newly completed drive and close the outbound drive for reconstruction.  We will also be improving the geometrics of the intersection with a right turn deceleration lane and the traffic signal will be upgraded. 

Please drive with care as you enter and exit the complex.  Phase 4 should be completed around September 30, 2013.

                             

All parking lots, except for the police visitor lot, will be open for visitor and employee parking at this time. The police visitor lot will remain closed and police visitors will continue to use the East Town Hall parking lot. Police visitors please use the sidewalk path along Town Hall to the front of the Police station.  For employees, the Sally Port and vehicle fueling area will continue to be closed.

 

We are about to the end of our construction schedule. The last phase of the project will be to apply a final layer of asphalt to the entire Civic Center Complex. The last phase is slated to begin on October 7, 2013.

 

Thank you all for your continued patience and cooperation.  The Project is progressing smoothly and should be competed by the end of October.

Phase 5

Final Asphalt Course for entire Complex

Completed on or before October 25, 2013

 

During this phase, the final top course of  asphalt will be applied to all the complex parking lots and Civic Center Drive.  This work will progress quickly.  Watch daily for signage and direction.  More information will be provided as it becomes available.   

 

As part of this last phase, the contractor will complete various items of work and install permanent signage and pavement markings.