West Bloomfield Logo                  
Contact Us | Jobs | FAQ
 
Subscribe to email notification
Facebook
Twitter
Google site search
  
  

Right-Of-Way

 

General Information

Permit Applications, Terms, and Conditions

 

 
   
 
 
Right-of-Way Permit Overview

 

All utility companies are asked to please read the Right-of-Way Disruption Permit Process Overview before applying for a permit. The application fee is $2500 and the permit fee is $500 per week. There is also a Restoration Surety fee of $1000 which is refunded after an inspector from the Engineering Department verifies complete restoration of the area.

 

Engineering Department Homepage